Skip to content

NYC building deadlines

NYC building deadlines in October

October has three dated NYC building deadlines. Heat season starts October 1 and runs to May 31. The new energy grade label must be posted near each public entrance within 30 days after October 1. October 31 ends the bedbug reporting year, which owners file between December 1 and 31.

October 1: heat season starts (residential)

From October 1 to May 31 the owner must provide heat; hot water is required all year. The boiler inspection runs on the calendar year, so a boiler not yet inspected this year can be done before the first cold week instead of in December. Boiler inspection: $509.

By about October 31: the energy grade label (both)

Buildings that benchmark get a letter grade each year. The label has to be printed and posted in a conspicuous spot near each public entrance within 30 days after October 1. Not posting it on time costs $1,250.

Grades run A to D by score, with F for a building that did not benchmark and N for exempt. An F means the building did not benchmark on time in May. Benchmarking.

October 31: the bedbug year closes (residential)

The HPD bedbug report covers November 1 to October 31. Rental building owners report how many units had an infestation and how many were treated. Pull the numbers from your pest control records at month end, while they are fresh. The filing itself opens December 1.

What October sets up

  • November 1, cooling tower certification (any building with a tower). Every tower operated this year needs its annual certification by November 1, and a Qualified Person certifies the maintenance plan. Book in early October. Get a price.
  • December, elevator spacing. A periodic inspection must be at least three months from the last CAT1 test. A CAT1 run in October pushes that elevator's periodic past December 31. Check both dates now.
  • HPD registration. The bedbug report can only be filed while the building's HPD registration is current.

Questions

What NYC building deadlines fall in October?

Heat season starts October 1, the energy grade label must be posted within 30 days after October 1, and the bedbug reporting year ends October 31. The cooling tower certification follows on November 1.