Yes — an asbestos survey by a licensed inspector is legally required before any renovation or demolition of a building constructed before 1987 in New York City. Here's exactly what the law requires, what an ACP-5 is, and when you're on the hook.

The Legal Requirement


Yes, asbestos inspection is legally required before renovation or demolition in New York City buildings constructed before 1987.


NYC Administrative Code §24-146 and the NYC Department of Environmental Protection (DEP) Air Pollution Control Code require that before any renovation or demolition work disturbing building materials, the building owner or contractor must:


1. Conduct an asbestos inspection by a NYS DOL ICR 56-licensed asbestos inspector

2. Determine whether asbestos-containing materials (ACMs) are present in the areas to be disturbed

3. If ACMs are present, conduct proper asbestos abatement before proceeding with renovation


This is not a contractor best practice — it is a legal prerequisite. Building permits for renovation in pre-1987 NYC buildings require asbestos documentation.


What Is the ACP-5 (Asbestos Control Program Form 5)?


The ACP-5 is a form filed with the NYC DEP before the start of construction or demolition. It certifies that either:

  • No asbestos-containing materials are present in the area to be disturbed (based on an inspection by a licensed inspector), OR
  • ACMs are present and abatement has been or will be performed per NYC DEP requirements

  • The ACP-5 is required for any alteration or demolition permit application at the NYC Department of Buildings. Without ACP-5 clearance, building permits are typically not issued for pre-1987 buildings.


    When the Pre-1987 Rule Applies


    The 1987 cutoff reflects when the EPA's asbestos ban in most new construction products took effect. Buildings constructed before 1987 may contain:

  • Asbestos floor tiles and floor tile mastic (pre-1980 9"×9" and 12"×12" vinyl tiles are presumed ACM under AHERA)
  • Pipe and duct insulation (particularly on heating/cooling systems installed before 1975)
  • Boiler and tank insulation
  • Ceiling tiles (acoustic ceiling products pre-1978)
  • Joint compound/drywall finishing compound (pre-1978)
  • Roof felt and tar
  • Window caulking and glazing compound
  • Certain plaster mixes

  • Buildings constructed after 1986 are generally exempt from the pre-renovation survey requirement, though asbestos may still be present in materials added during subsequent renovation.


    What If ACMs Are Found?


    If the inspection identifies ACMs in the areas to be disturbed, renovation cannot proceed until:


    1. A licensed asbestos abatement contractor (NYS DOL ICR 56 / NYC DEP licensed) removes or encapsulates the ACMs

    2. Air clearance testing confirms the work area meets OSHA and EPA standards

    3. Abatement is documented in the project file


    Disturbing ACMs during renovation without abatement is a serious violation of federal (OSHA 29 CFR 1926.1101, EPA NESHAP) and NYC regulations, and creates liability for the building owner, contractor, and workers.


    The Nassau/Suffolk/Westchester Difference


    Outside the five NYC boroughs, the applicable regulation is NYS Industrial Code Rule 56 (ICR 56) — the state asbestos standard. ICR 56 requires asbestos inspection before renovation that disturbs more than threshold quantities of suspect material. The NYC-specific ACP-5 filing and NYC DEP license are NOT required for work in Nassau, Suffolk, or Westchester County. However, the inspection must be conducted by a NYS DOL ICR 56-licensed inspector — a different (and sometimes additional) credential from the NYC DEP contractor designation.


    All 123inspections asbestos inspectors hold NYS DOL ICR 56. Inspectors serving NYC boroughs also hold the NYC DEP Air Code certification.


    Practical Steps for Homeowners Planning Renovation


    1. Before hiring a contractor: Hire a licensed asbestos inspector to survey the areas that will be disturbed

    2. Get a written survey report: This documents what was found and is required for the ACP-5 filing

    3. If no ACMs are found: Proceed with renovation; the inspector's report supports your ACP-5 filing

    4. If ACMs are found: Hire a licensed abatement contractor before renovation begins; do not ask your renovation contractor to "deal with it" — this creates enormous liability


    Do not rely on a contractor's verbal assurance that there's "probably no asbestos." The legal obligation is yours as the building owner.

    Regulations Referenced

    Quick Answers

    Is asbestos inspection required before home renovation in NYC?
    Yes. Under NYC Administrative Code §24-146 and the NYC DEP Air Pollution Control Code, an asbestos inspection by a NYS DOL ICR 56-licensed inspector is required before any renovation or demolition that will disturb building materials in a building constructed before 1987. An ACP-5 form must be filed with NYC DEP before building permits are issued.
    What is an ACP-5 form?
    The ACP-5 (Asbestos Control Program Form 5) is a form filed with the NYC Department of Environmental Protection before construction or demolition. It certifies either that no asbestos-containing materials are present in the renovation area (based on a licensed inspector's survey), or that ACMs are present and abatement will be performed. ACP-5 clearance is required for most NYC building permits in pre-1987 buildings.
    Book a Related Inspection
    Asbestos Testing